|
By Pete Stidman
News Editor
The Massachusetts Water Resources Authority this
week said it is still open to negotiations on a
tense standoff over the design of an "odor control"
facility on Columbia Point, but Joseph J. Corcoran
- whose company plans a billion-dollar development
next door - is sticking to his guns, saying
Corcoran Jennison Cos. should not have to pay an
extra dime to make sure the neighborhood isn't
impacted by fumes.
"The authority has been able to complete an
awful lot because we have been able to maintain
community and neighborhood support," said Fred
Laskey, executive director of the MWRA board. "So
if we can come to some sort of agreement and make
Mr. Corcoran happy, we think that's a good
investment."
The disagreement is a classic case of "not in my
back yard" - or at least not like that - save that
the closest back yard is owned by a single
developer who has submitted plans to the city for a
billion dollar development that would create
several entire blocks of new retail, office and
residential space, including new roads and other
infrastructure on the site of the Bayside Expo
Center. All of which could bring in significant
revenue for the city and the state.
To build all that, Joe J. Corcoran said this
week that he cannot have even the possibility of a
stink ruining a meal at an al fresco restaurant
come May 2011 when the odor control facility is set
to be finished. That unknown factor would not sell
well to prospective tenants.
The odor control facility will sit atop an
18-million gallon tunnel that extends 2.1 miles to
near Castle Island. The tunnel is part of a vast
court-ordered project to capture stormwater - that
combines with raw sewage in Boston's old sewer
system during heavy rains - and send it out to Deer
Island for treatment.
When finished, it may make Carson Beach one of
the nations' cleanest urban beaches.
Rain events that would trigger combined
stormwater-sewage outflow would occur an average of
20-times a year, according to the MWRA. And
Corcoran's odor engineer is worried about heavier,
peak rain events, which are less frequent.
If the facility goes forward as planned,
Corcoran said, he would be forced to drastically
change the nature of Bayside on the Point, taking
out the outdoor shopping aspects and perhaps
focusing on an office park or indoor shopping.
And, according to Tech Environmental's Michael
Lannan, a consultant to Corcoran, during peak rain
events a wide swath of Dorchester and South Boston
could be affected if the MWRA is wrong.
"This isn't a Corcoran and MWRA dispute," said
Corcoran. "This is the MWRA and the community.
We've done everything we can do with the MWRA. The
community has to step in and take it from here
because we don't think those plans will work."
Catherine O'Neill, communications director at
Corcoran Jennison, plans to take the issue to civic
associations and others in the neighborhood in the
coming weeks.
"That's all I'm going to be doing," she
said.
Laskey says that the MWRA is still open to
negotiations and counter-offers, but he added that
each day the window for compromise gets smaller. In
order to meet court-ordered deadlines, the MWRA
figures the design for the facility would have to
be complete by April. And an underground design,
which Corcoran is pressing for, would take longer
to draw up.
The odor control facility, as the MWRA proposed
it, uses activated carbon filters to treat the
stinky air, which is pushed out of the tunnel by
incoming stormwater and released from a
40-foot-high stack. Lannan contends that the wind
blowing in from the ocean would flow over the
35-foot high brick building next to the stack that
houses two giant fans, carrying the smells from the
40-foot high stack down to the ground on the other
side, where neighbor's noses might be.
If it was underground, he said, that "downwash"
effect would be eliminated.
"Our argument is we're so far below the level
that is noticeable that it doesn't matter if
there's a downwash," Laskey said this week.
"Why not build in an extra redundancy?" said
Corcoran. "They should be very conservative in how
they approach this."
The two sides have been negotiating and studying
the design behind closed doors since November 2006,
when the MWRA first notified Corcoran of the
easement onto their property. The MWRA offered to
split the $3 million extra that the agency says it
would cost to sink the facility, but Corcoran
balked.
Corcoran suggested the MWRA commandeer some of
the money the company will have to pay the Boston
Water and Sewer Commission to build new plumbing
for the new Bayside on the Point, but the MWRA
refused.
So last month, the MWRA board voted to move
forward with their original design, a 35-foot vent
house with a 40-foot stack.
As the Reporter
first reported on Nov. 20, Corcoran then
promptly informed the city that he would have to
halt his project. Corcoran contends it would cost
only $1 million extra if the machinery were
designed on a smaller footprint, his company
wouldn't have control over costs, and he is adamant
he will not pay a dime for it anyway.
"That's the principal of it: 'Why does a private
guy have to pay for something that's done right?'"
said Corcoran. "I'm not suggesting they do anything
extra, I'm suggesting they do it the right
way."
Members of nearby civic associations are not
exactly scrambling to tackle the issue, and strong
feelings on either side are hard to find.
"This is a tough one," said Millie Rooney from
the McCormack Civic Association (also the wife of
Jim Rooney, who oversees the Boston Convention and
Exhibition Center). "Maybe somebody needs to come
in besides the MWRA and Corcoran to tell people:
'Yes, this should go underground,' some kind of MIT
professor or something. If I got that I'd be
willing to go the extra bucks."
"We decided we're going to proceed with
caution," said Deirdre Habershaw, president of the
Columbia Savin Hill Civic Association. "We need to
have a few more discussions internally."
Both will have representatives at a meeting of
the Columbia Point Master Planning Task Force, 5
p.m. on Dec. 18 at BC High School, where the MWRA
is expected to present their design.
Earlier coverage
Odor
facility clouds future of Bayside project - Nov.
20, 2008
Odor
control facility raises new questions on Columbia
Point- Feb. 21, 2008
Back
to Reporter Home Page
|